Solar Encapsulation Interlayer Film Manufacturing Plant (EVA / POE / EPE)
Capacity: ~1 GW Equivalent (8.5–10 Million m² per annum)
1. Executive Summary
This Detailed Project Report (DPR) covers the establishment of a state-of-the-art Solar Encapsulation Interlayer Film Manufacturing Plant producing EVA, POE, and EPE films used in crystalline silicon solar PV modules.
The proposed facility is designed around a GWELL/GW-type high-end extrusion line with advanced melt pumping, precision T-die, five-roll calendering, X-ray thickness measurement, and fully automated winding. The plant is sized to support ~1 GW of solar module production per annum, equivalent to 8.5–10 million m² of encapsulation film.
The project targets:
2. Project Objectives
3. Product Description
3.1 Product Types
|
Product |
Typical Thickness |
Application |
|
EVA Film |
0.45–0.65 mm |
Mono / Poly PERC modules |
|
POE Film |
0.4–0.6 mm |
N-type, TOPCon, HJT |
|
EPE Film |
Dual-layer |
High PID resistance modules |
3.2 Key Specifications
4. Plant Capacity & Throughput
4.1 Line Output
4.2 Annual Production
Assuming:
|
Parameter |
Value |
|
Annual polymer consumption |
~6,000–6,500 MT |
|
Film output |
8.5–10 million m² |
|
Solar capacity equivalent |
~1 GW/year |
5. Manufacturing Process Flow
6. Major Equipment Summary
6.1 Extrusion & Melt System
6.2 Forming & Calendering
6.3 Automation & Quality Control
6.4 Winding & Finishing
7. Utilities Requirement
6A. Plant Layout & Area Requirement
6A.1 Main Production Line Footprint
Based strictly on the supplied installation dimensions for the complete EVA/POE/EPE extrusion line:
Net machine footprint area:
25 m × 6 m = 150 m²
Enclosed volume (for HVAC / fire design):
25 × 6 × 8 = 1,200 m³
This height is mandatory to accommodate:
6A.2 Mandatory Working & Safety Clearances
For safe operation, roll handling, maintenance, and statutory compliance:
|
Item |
Allowance |
|
Operator access (both sides) |
+1.0 m each side |
|
Electrical panels & walkways |
+1.5 m |
|
Winder roll handling zone |
+6–8 m length |
|
Maintenance clearance (ends) |
+2 m |
Effective operational footprint:
Operational area per line: ≈ 350 m²
6A.3 Ancillary Areas (Same Building)
|
Section |
Typical Area (m²) |
|
Raw material storage (EVA/POE pellets) |
300–400 |
|
Mixing & dosing (conical mixers) |
120–150 |
|
Edge‑scrap recycling extruders |
80–100 |
|
QC / testing lab |
80–100 |
|
Electrical room & PLC |
50–70 |
|
Finished roll storage |
400–500 |
6A.4 Total Built‑Up Area Requirement (1 Line – 1 GW)
|
Area Component |
Approx. Area |
|
Main extrusion line (operational) |
~350 m² |
|
Ancillary production areas |
~900–1,100 m² |
|
Utilities, passages, safety margin |
~250–300 m² |
Total recommended covered area:
1,500 – 1,750 m²
6A.5 Structural & Civil Recommendations
7.1 Electrical Power
7.2 Water
|
Type |
Requirement |
|
Circulating cooling water |
35–40 m³/hr |
|
Chiller water |
<0°C to 10°C |
|
Pressure |
4–6 bar |
7.3 Compressed Air
8. Manpower Requirement
|
Category |
Nos./Shift |
|
Line Operators |
6 |
|
QC / Lab |
2 |
|
Maintenance |
2 |
|
Supervisors |
1 |
|
Utilities & Stores |
2 |
Total manpower (3 shifts): 40–45 persons
9. Quality & Standards
In-house testing:
10. Environmental & Safety Aspects
11. Project Cost Estimate
Project cost is not expressed in monetary terms in this DPR, as it varies significantly based on the final technical configuration of the production plant.
The total project investment depends on multiple interlinked technical and commercial parameters, including but not limited to:
Accordingly, project cost must be evaluated on a case-by-case basis after finalisation of the above parameters in discussion with equipment OEMs and technology partners.
For reference only (non-binding):
FOB equipment price depends on full A–Z technical configurations, however it may typically range from USD 650,000 up to USD 1,000,000 FOB, subject to final scope, automation level, materials, and performance guarantees.
12. Financial Highlights (Indicative)
13. Implementation Schedule
|
Activity |
Duration |
|
Order finalization |
1 month |
|
Manufacturing of line |
6–7 months |
|
Shipment & erection |
2 months |
|
Trial & stabilization |
1 month |
Total project duration: 10–11 months
14. Risk & Mitigation
15. Conclusion
The proposed 1 GW EVA/POE/EPE solar encapsulation film plant is technically robust, future-ready, and commercially attractive. With advanced European–Chinese hybrid equipment configuration, the facility is suitable for supplying Tier-1 solar module manufacturers in India and global markets.